The strip of promising pines in Jančova Street is in direct intervention by the planned changes and building modifications. In such cases of conflict between the building and valuable greenery, the procedure is in accordance with ČSN 83 9061 Protection of greenery during construction activities, which clearly determines the procedures that must be followed to minimize damage to trees. Continue reading “Perspective pine in Jancova street”
Category: Jančova
First parking spaces available
On Monday 12/5, the first new parking spaces, which were created within the Letňany lentils, were handed over for early use. There are a few places in Jančová Street and another at the end in Ivančická. Parking has been a big topic since the first Lentilek study was published. Especially in Ivančická it can be seen that the designers were looking for practically every meter that could be used for cars. Continue reading “First parking spaces available”
Current schedule of Lentilky
Letňany lentils are not an exceptional building that differs from others. Some activities go slower, others faster. In Ivančická we discovered panels under the grass. Next to Místecká 448, where a new car park is already open, there were again problems with sewerage. These are standard unpredictable issues that are addressed on every construction site. Click on the side image to see the current schedule valid at the end of May.
Current schedule of Lentilky
Letňany lentils affect the lives of thousands of people in the housing estate and are not an exceptional building that differs from similar buildings in residential areas. Some activities go slower, others faster. In Ivančická we discovered panels under the grass. Next to Místecká 448, where a new car park is already open, there were again problems with sewerage. These are standard unpredictable issues that are addressed on every construction site. The situation changes every day. Continue reading “Current schedule of Lentilky”
Jančova will be open after the weekend
From next year, drivers will be able to use dozens of new parking spaces. Jančova Street has been given a new surface and vertical parking spaces will be on both sides. As part of the Lentilek project, the original pines were also preserved, for which special protective countermeasures were implemented during construction. Jančova will be passable along Kuželova Street for the time being, it will be completely open until Ivančická in October.
The car parks in Místecká and Kuželova streets will be closed from 21/7
The car park in front of Místecká 567 – 569 will be closed from 21/7. The entire crossroads Místecká x Jančova x Jablunkovská will be impassable for several weeks. Before closing the whole area, Jančova Street will be opened with dozens of new parking spaces. Drivers can park their cars in newly created places.
Kuželova Street will also be closed from 21/7. Entry will be allowed only to construction machinery and cars of the construction contractor. We apologize to the drivers for the traffic restrictions.
More parking in Jančov
The first new part of Jančová Street is open from 21/7. Dozens of new parking spaces could be filled by drivers the weekend before the opening. Jančova Street has been given a new surface and vertical parking spaces are on both sides. As part of the Lentilek project, the original pines were also preserved, for which special protective countermeasures were implemented during construction. The entrance to the street in the coming weeks will be only from Místecká. Drivers will fully enjoy Jančov from October. Continue reading “More parking in Jančov”
Thanks to Mr. Třešňák
Mr. Josef Třešňák lived in a family house on the corner of Jančová and Místecká streets for over 40 years. An experienced metalworker has been retired for several years, and therefore he had the opportunity to monitor the construction of Letňany lentils every day. In early June, when it was very hot, he helped builders adhere to their drinking regime. Mr. Třešňák, thank you for supporting the Lentils.
Current schedule of Lentilek
Construction is still in full swing to be completed in the fall. A rocking lantern was opened behind the house in Ivančická Street. Parking in the part of Jančová street is available, work is being done on the new square near Žabka. Kuželova Street and part of Malkovského in the courtyard with the house Místecká 448 – 453 have disappeared. The pyramid is already standing, but a fence will still be built, so it is not yet open to children. Work is also continuing on the sports lentil in Místecká, where the basics can already be seen. Continue reading “Current schedule of Lentilek”
The housing estate will be ZONE 30
As part of the Letňanská lentilka project, traffic in the housing estate will also change significantly. New parking spaces have been added for drivers and road surfaces have changed. Some crossings have been modified to protect pedestrians. Traffic calming is achieved by retarders and other deceleration elements. The Lentilek housing estate is now ZONE 30. What does this mean for drivers? Continue reading “The housing estate will be ZONE 30”